MEMME completed the Jane and Shoreham Basement Flooding project by installing 2.4 km of storm sewer (up to 1800 mm diameter), new watermain sections, and all affected residential sanitary and water services, finishing with full road restoration.
Working in a dense residential area near Black Creek, we managed strict work-hour restrictions and ensured safety by controlling creek backflow during heavy rain and melt events, along with sewer bypass pumping. We realigned existing watermain to fit larger storm sewers and completed all commissioning.

A comprehensive schedule and traffic management plan guided the work, including lane closures, detours, and coordination with local schools to maintain safe student access. The project involved installing a deep storm sewer through a major intersection while working around critical utilities and maintaining traffic flow.

Despite a six-month delay from a Toronto Hydro conduit redesign, MEMME stayed on standby and helped reschedule to meet the updated timeline successfully.

GALLERY